We are buliding a gas plant. As EPCC and in order to optimize the extent of fire proofing application for the Pie racks structures as well as structural steel skids (supporting gas treatment vessels), I remember that for:

-  Pipe racks fire proofing application is up to 3 m height from the pole base. Only the poles.

- Skids: Only saddles and their suppoting beams onthe skid

are subject to fire proofing.

Please share your experience in this field and applicable STD.

Thanks

--
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAOzUbK5U8PWo1L4R3ja4rv6ozd_U%2BfyUmXpvmGteAHw5_qz1sw%40mail.gmail.com.
For more options, visit https://groups.google.com/d/optout.

No comments:

[MW:34919] Welder qualification certificate

Dear All     anyone can share a format for welder certificate and card format        Thanks & Best Regards Saleem manhappulath Mob:+9665...