Hi Mr.Neilash Kumar,

If you are doing Vessel you have to check with API RP-934 A.There is mentioned requirements of dehydrogenation treatment  (post heating).


On Thursday, April 7, 2016 at 11:09:18 AM UTC+3, neilash kumar wrote:


Dear All, 

Good Day ! As per our client aramco , insisting us to do dehydrogenation treatment for P11 material after welding completion for four hours prior to PWHT.

Please clarify whether post heat maintainence for 4hours is mandatory for fillet weld.

As per our WPS  I am doing it for  groove joints , it is clad vessel for 145 inch diameter ... 

Above that insulation and pad welding Accor , is there any clause given in ASME section states that post heat maintainence is not required for P11 material.


As per aramco standard SAESW014 General it is given


P.NEILASHKUMAR 
Sent from my iPad
MOB : 966 551094590
            + 91 9952110791

--
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/879882df-bb20-472e-8470-3b89fd86df01%40googlegroups.com.
For more options, visit https://groups.google.com/d/optout.

No comments:

[MW:34919] Welder qualification certificate

Dear All     anyone can share a format for welder certificate and card format        Thanks & Best Regards Saleem manhappulath Mob:+9665...