Friday, October 23, 2015

[MW:23779] Vessel Design Temperature Change


Dear All,

I have situation where Air Receiver Vessel made of SS 316  designed as per ASME SEC VIII DIV 1 U stamped shipped to site but not yet installed. The vessel is stored on warehouse in packed condition.

 

The Present design temperature is 70°C which need to be changed to 85°C.

 

Can you please suggest which are steps we have to take ? Any code reference for recertification ?


 

Regards

Praphulla

No comments:

[MW:35597] INCONEL 825

Dear all  INCONEL 825 matching filler   ER NI FECR-1 its correct please guide me Regarding  Elavarasan -- https://materials-weldin...