Dear Vino,
You need to demonstrate real hardware. Past records will demonstrate only one chapter of your ASME Quality Control Manual, ie, Record retention.
Since you have Div 1 & 2, you should demonstrate both codes.
1. Div 1: Actual vessel or demo vessel along with calculation
2. Div 2: A set of design calculation with drawing, uSER Design specification +Manufacturers Design report + Material purchase specification
Arun
On 17 October 2012 11:01, Vino Varghese <vinopvarghese@gmail.com> wrote:
--Dear Experts,Please share information with regard to Re-Certification requirements of ASME Sec VIII Div 1 & 2.Our company is organising to have this done in Mar'13.Do we require any ongoing Pressure Vessel for Re-Certification or any previous completed Vessel in 2012 can be considered for Re-Certification.I appreciate if you have a built guidelines for the same to share...Thanks & RegardsVino - Doha
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
--
Arunachalam.A,
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm