yea it has mentioned in AWS D1.1 cluase 5.17.3
--
-- On Mon, Jan 16, 2012 at 12:52 PM, jesti fer <jesti_fer@yahoo.com> wrote:
--Dear Experts,I need your help for this subject, We are fabricating some piping as per B31.3, the material ASTM A106 Gr.B, 8"Sch-XXS and 160 and we are doing preheat and PWHT for welding, but my enquiry pre heat is required for cutting also? It is mentioned in any code or any other were? Please help meJesti
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
Best regards,
Tarek Yehia
Tarek Yehia
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
No comments:
Post a Comment