[MW:4204] packling&passivation after hydrotest is ideal?

Friends
 
I have a vessel with MOC SA 387 11 cl-1class11 with  410S cladding(Coke drum). The vessel is to undergo PWHT and external blasting and painting.
Please suggest if I go for pickling&passivation after hydrotest that will be more appropriate? In my earlier projects I have done picking&passivation before hydrotest.
What is the best practise? Please advise.
 
Regards
Hrishi

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:34916] Applicability of Impact requirement as per ASME B31.3

Dear All, Design code – ASME B31.3, Welding Code- ASME BPVC SEC IX Material  to be used used during Fabrication - SA 333Gr6 (P No.1 G...