Saturday, June 29, 2019

Re: [MW:29766] WPS by ASME and WPQT by Indian Standard

Hi,

None can be entertained whether he is client or owner with reference / evidences.

So what was your contractual agreement, any written documents by both parties on following standards international / clients manual cut off what to be followed?

Its all depend upon writings, what has written to be followed, if you are right and still client is insisting you for non mandatorial requirement highlight to your upper management.

Yours
MOHAMED MUNEEB MAHABOOB
+91-786-700-444-6      TRZ - INDIA
''quality is not your cup of tea to waive as per your own business conditions - quality is that tree fixed firmly deep rooted, in which each root is an evidence of references''
 
Date: 2019-06-25 17:10
Subject: [MW:29746] WPS by ASME and WPQT by Indian Standard
Hello all,

Our company received an order in which client is insisting welder qualification to be done as per IS 817, and ASME WPS can be used .

Now my doubt is can we usw ASME WPS to qualify welder in IS.

Regards,
Dattu.

--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
Visit this group at https://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/4d703331-5781-4add-af53-f06cc7e0099d%40googlegroups.com.
For more options, visit https://groups.google.com/d/optout.

No comments:

[MW:34920] Tubesheet Hole step

Hello Team, I have one question any tolerance given for tubesheet Hole step. Please do needful. Regards, AP  -- https://materials-...