Thursday, November 1, 2018

Re: [MW:28545] Re: Query About WPS

2layer, better minimum 6mm smaw
THANKS & BEST REGARDS,
KG.PANDITHAN, BE, IWE,  CSWIP 3.1,
ASNT-Level II in PT,MT,RT & UT.
International Welding Engineer. 
CONSULTANT-WELDING & QUALITY
Mobile no: +919940739349


On Thu, Nov 1, 2018 at 12:12 PM Hasin Shaikh <hasin.shaikh@gmail.com> wrote:
Thanks

Is it ok if we use in backing first Run with SMAW AND further subsequent Saw weld?

Can you provide me any clause of sec-9 acceptance or non acceptance.
 Regards

On Mon, 22 Oct 2018 at 8:32 AM, sandeep kumar <sandeepdhiman63@gmail.com> wrote:
according to section 9, deletion of backing & joint design are non-essential variable, Refer QW 402.1 & 402.4. So there is no issue. 
However in SAW, you need to have backing material either as removable backing strip or permanent backing to hold the high heat & weld penetration. in thumb rule, the depth of penetration in SAW is 0.1 X 100 amp for square butt and 0.7 X 100 amp for Y groove welds.

In your case, you have to make separate WPS based on your PQR for SAW only, which should clearly state the applicable proper joint configuration & welding pass sequence.

Thanks & regards
Sandeep Kumar

On Friday, October 19, 2018 at 6:53:31 AM UTC+3, hasin shaikh wrote:

Dear All,

question about weld process use,
 WPS & PQR Based on two process with back-chip and welding

as in PQR Process use in root SMAW and subsequent SAW and back chip with SMAW weld.
in this case can we use SAW PROCESS for back welding? FOR production weld?
--
*With Regards
Shaikh.Hasin



--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
Visit this group at https://groups.google.com/group/materials-welding.
For more options, visit https://groups.google.com/d/optout.
--
Hasin Shaikh
+91-9924562942

--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
Visit this group at https://groups.google.com/group/materials-welding.
For more options, visit https://groups.google.com/d/optout.

--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
Visit this group at https://groups.google.com/group/materials-welding.
For more options, visit https://groups.google.com/d/optout.

No comments:

Re: [MW:35289] Welding consumable for S355J2WP material

S355 J2 WP  is a weathering structural steel  It has better atmospheric corrosion resistance. Use E 8018 - W1/W2  Electrodes This is regular...