Thursday, April 7, 2016

[MW:24643] Intermediate stress relief treatment



Dear All, 

Good Day ! As per our client aramco , insisting us to do dehydrogenation treatment for P11 material after welding completion for four hours prior to PWHT.

Please clarify whether post heat maintainence for 4hours is mandatory for fillet weld.

As per our WPS  I am doing it for  groove joints , it is clad vessel for 145 inch diameter ... 

Above that insulation and pad welding Accor , is there any clause given in ASME section states that post heat maintainence is not required for P11 material.


As per aramco standard SAESW014 General it is given


P.NEILASHKUMAR 
Sent from my iPad
MOB : 966 551094590
            + 91 9952110791

No comments:

[MW:35346] Cast-iron welding

Any advice for cast iron welding Sent from Yahoo Mail for iPhone