We have crude and petroleum tanks in which 1 course of shell plates PWHT has to be carried out, so our subcontractor erect and install first , second and third course shell plate I asked if we could start welding in the second course and complete tanks shell without welding vertical and horizontal of the first course, and I want some document from code to approve this method if correct.