[MW:15716] Visual Inspection after Machining of Valve Casting (Ball On off Valve

Dear Expert,

 

I need your Support Regarding Visual Inspection of Casting ( after or before  Machining)

 

 

1)      It is possible to do Visual Inspection after Machining of Valve Casting (Ball On off Valve) ?

Because Saudi Armco spec does not Specify Regarding these 04-SAMSS-048 or MSS SP 55.

If Have any reference please provide OR otherwise give your valuable suggestion.

 

 

 

Regards,

 

Shaikh Ahmed

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
 
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
 
 

No comments:

Re: [MW:35289] Welding consumable for S355J2WP material

S355 J2 WP  is a weathering structural steel  It has better atmospheric corrosion resistance. Use E 8018 - W1/W2  Electrodes This is regular...