Sunday, January 10, 2010

[MW:4005] UW-31 - Cutting, Fitting & Alignment, Forming of Manway neck & Tacking on Long seam at subcontractors end.

Dear All,
 
I have a following Issue with regards to above subject.
 
1. Issue: We had subcontracted the rolling of Manway neck/ Pipe and it needs to be tack welded.
 
2. Query:
 
1. Whether, the subcontracctor can tack weld the pipe if he submits the Proper WPS, PQR & Welder qualification records ? or,
 
2. Can we send our welder to his shop for tacking the long seam using our company WPS ? As our 'U' Stamp certification scope allows us to manufacture pressure vessel at field sites controlled by us.
 
 
3. Statement in UW-31(c): 2nd Paragraph
 
" Provided that the work is done under the provisions of U-2(b), it is not necessary that a subcontractor making such tack welds for a vessel or parts manufacturer be a holder of Code Certificate of Authorization. Th requirement of UW-26(d) do not apply to such tack welds."
 
Statement in U-2(b):
 
(1) The manufacturer of any vessel or part to be marked with the code symbol has the responsibility of complying with all of the applicable requirements of this division, through proper certification ( I consider WPS,PQR & Welder qualification records of subcontractor), of assuring that all work done by others also complies.
 
Also, If anybody is having the intrpreatation of above clause of ASME, then please let me know or provide it if possible.
 
Ajay
 
 

1 comment:

Anonymous said...

nice post. thanks.

Re: [MW:35289] Welding consumable for S355J2WP material

S355 J2 WP  is a weathering structural steel  It has better atmospheric corrosion resistance. Use E 8018 - W1/W2  Electrodes This is regular...