Skip to main content

[MW:1238] Hydro test-max holding period


The holding period depends on the time needed for inspecting the system thoroughly. Minimum is 10 minutes. Especially the gas tests calls for 100% weld and mechanical joints being examined.
Also we have to ensure the limits of test pressure defined by individual components also to be taken care not to damage the components for eg. the soft seating or lining or to replace them with pipe spools.

To my info the repeated call for Hydrostatic test on the same system, the pressure need not be changed from the code to its design pressure as most of the case if any major leaks are identified, the test is performed again at the same pressure and not to reduced pressure. It is independent of the holding time. Holding time risk are purely defined by inspecting time and the in-line components and not of the piping components. It is a usual practice to remove all in-line components which has reduced testing pressure conditions.

The maximum test pressure is the pressure at which the pipe reaches its yield stress. In most of the cases the problems can be tracked back to the original thickness calc of the piping system where in somecases you may find the thickness not sufficient to take the test pressures but will suit the design pressure. When you design the piping class for rating condition you may have some margins to accommodate the test pressure but not always especially in the larger size range above 24". This makes the site testing team to reduce the test pressure adjusting to actual pipes purchased and being used and of the elevation impact of the system. Also piping connected with vessels pose a diff. situation and defining the test pressures requires a different judgement as the approach differs from company to company.

Most important thing is to question the need of hydrotest for a system to process dept. who defines the requirement.

Regards,
Kannan.



Aarpee <ramprasad.chari@gmail.com>
Sent by: materials-welding@googlegroups.com

24/10/2008 08:29

Please respond to
materials-welding@googlegroups.com

To
"Materials & Welding" <materials-welding@googlegroups.com>
cc
Subject
[MW:1236] Hydro test-max holding period






As per B31.3 Hydro test is carried out at 1.5X Design Pressure.Holding
time for Piping spools is normally 30 minutes but at times 4-6 hours
for Gas applications.Can this be held for 24 hours?What is the
potential risk?It is normally indicated that after Hydro inspection
for 10-30 minutes at 1.5X Design Pressure,if you intend doing further
inspection then same can be done at a pressure not more than the
design pressure.Opinion of the group is being sought thro this mail
Regards
Aarpee

--~--~---------~--~----~------------~-------~--~----~
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
-~----------~----~----~----~------~----~------~--~---

Comments

Popular posts from this blog

Materails FAQs

Q: What are equivalents for standard Q 235 B (and Q 235 A) for U-channels? (asked by: boris.vielhaber@vait.com) A: DIN Nr. = 2393 T.2, 2394 T.2, EN 10025 W. Nr. DIN 17007 = 1.0038 Design DIN 17006 = RSt 37-2, S235JRG2 (Fe 360 B) Q: What is St DIN 2391 BK material? (asked by: dmcandrews@automaticstamp.com) A: Precision steel tubes, cold-finished/hard. Q: What is C.D.W. Boiler Tube? (asked by: montydude123@yahoo.com) A: Cold Drawn Welded Boiler Tube. Q: WHAT IS W.Nr. 1.4301? PLS TELL US IN EASY LANGUAGUE (asked...

Heat tint (temper) colours on stainless steel surfaces heated in air // Heat tint

Introduction The colour formed when stainless steel is heated, either in a furnace application or in the heat affected zone of welds, is dependent on several factors that are related to the oxidation resistance of the steel. The heat tint or temper colour formed is caused by the progressive thickening of the surface oxide layer and so, as temperature is increased, the colours change.   Oxidation resistance of stainless steels However, there are several factors that affect the degree of colour change and so there is no a single table of colour and temperature that represents all cases. The colours formed can only be used as an indication of the temperature to which the steel has been heated. Factors affecting the heat tint colours formed Steel composition The chromium content is the most important single factor affecting oxidation resistance. The higher the chromium, the more heat resistant the steel and so the development of the heat tint colou...

Re: [MW:10788] ON PLOT PIPING & OFF PLOT PIPING

Piping systems involved for the flow lines and gathering lines from the well head isolation valve to the production facility or processing plant isolation valve are determined as OFF PLOT. ON PLOT defines piping system in the processing plant and production platform. ANSI/ASME B31.4 applies for off plot piping system. B31.4 allows the use of either API 1104 or ASME section IX (as appropriate). However, occasionally, a very small system such as piping within 500 feet of a processing plant (some client also said 400 feet) may be declared B31.3 rather than B31.4. When B31.3 is invoked, only ASME Section IX is used. before you decide which code to use for welding procedure and/or welder qualification for pipe welding, you have to know the design and construction code applicable to the system. Please read far enough into scope and diagram illustrating the application of either B31.3 and B31.4 hope this helps rgds 2011/4/21 pradip kumar sil < pradipsil@gmail.com > Dear all, ...