There is chapter related to :
QUALIFICATION TESTS FOR WELDERS ENGAGED IN WELDING OF BOILERS AND STEAM-PIPES UNDER CONSTRUCTION, ERECTION AND FABRICATION AT SITE IN INDIA AND IN REPAIRING BOILERS AND STEAM-PIPES BY WELDING
WPS PQR are not required.
Thanks and regards
Vishwas
IWE
On Thursday, January 26, 2023 at 2:42:13 PM UTC+5:30 Anand Elankumaran wrote:
Dear Experts,Could you please provide the details about the IBR Welding requirements in terms of WPS & PQR, WQT.--Thanks and Regards,E. Anand,Lead QA-QC,Sohar,Oman.
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/a9be3b62-05c9-47d2-9f83-9a59a27c2e1fn%40googlegroups.com.