Good Evening, In our project Vessel joint thickness 10mm ,Process(GTAW+SAW),Single V joint
They completed Welding ,Few days later during Inspection we observed , They have done Internal Welding of the shell, As per WPS its not shown
Guys let me Know its can Accepted or Rejected
If Rejected , Please send Reference code standards
As per QW 402.5 Joints (Backing its non Essential ),Its mention Backing strip or also back welding