Equipment--- WING WALL PANEL.
MOC--------- Tube-SA213T91+Fin 12Cr1MoV
sizes---------Tube/Dia 42X6mm thick
Fin/ Width 18X6mm thick
After welding, there is lateral bend, To correct it we are doing HOT FLAME CORRECTION below Lower Critical Temp AFTER PWHT.
QUERY --- IS IT ADVISABLE TO DO SO, if not what is procedure.
THANKS®ARDS
KG.PANDITHAN, BE,IWE,AWS-CWI,CSWIP-3.1
Adviser/International Welding Engineer