Monday, May 29, 2017

[MW:26548] ASME B31.3 -2014 Table 331.1.1 Soaking time for P1 material

Hi Team,

Could any please clarify
What is the minimum required soaking time for P1 material with wall thick 12mm, as per ASME B31.3 year 2014 Table 331.1.1 .

Is it still Minimum one hour per 1 Inch wall thickness or Minimum 15 Minutes...


Regards,

Ram

--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
Visit this group at https://groups.google.com/group/materials-welding.
For more options, visit https://groups.google.com/d/optout.

No comments:

Re: [MW:35241] Overlay welding defects

Dear Sir, The below is another type of defect,Mostly these two type of defects we faced. Regards, R.Gowtham. On Wed, Sep 11, 2024 at 1:42 PM...