Dear Experts,

  Need your assistance.

Applicable code : ASME sect I
Query : 

1- For Pipes/tubes NPS less than 4" diameter, we need to perform NDE with some ratio, basically according code is not mandatory (table PW-11) : Please inform if any other indication about this issue in code.

2- Could us perform NDE (RT : Volumic) before pwht and complete only by (MT: Surfasic) after pwht for P91 and also for others grades according ASME sect I. What's code requirement for NDE/Pwht.
tat 

--

Thanks and Regards, 

--
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAD8EeB10jWyXzVrEm%2BmeA7tSfkTA6P0VWx9%3D%3DcUnJQZ6xEccxA%40mail.gmail.com.
For more options, visit https://groups.google.com/d/optout.

No comments:

[MW:34920] Tubesheet Hole step

Hello Team, I have one question any tolerance given for tubesheet Hole step. Please do needful. Regards, AP  -- https://materials-...