Dear Friends

We have one of the equipment in refinery service refractory lined

Process Licensor (UOP) prescribes dry out of refractory using Gas Firing

We had sent devaiton request to UOP for carrying out refractory lining using Oil firirng method,but same was rejected by UOP

Can any one inform me arrangement for gas firing method

Regards
Sachin.Sankhe

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.