Saturday, December 3, 2011

[MW:13128] Is it downcommers comes under saperate piping

For code vessel boiler , stam drum, risers & downcommers are sending
saperately to the site , at site these equipments are joined by
welding we are making equipment wise MPDR (manufacturers partial data
report) it is enough or for each equipment MDR (manufaxturers data
report ) required. Please reply me.

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:35346] Cast-iron welding

Any advice for cast iron welding Sent from Yahoo Mail for iPhone