You are not changing the PQR, only extracting two welding processes
from the three. Just ensure that the deposited weld metal thickess of
both GTAW & SAW process covers your requirements.
Regards,
On 3/5/10, SENTHILKUMAR SWAMINATHAN <skumarswami@yahoo.co.in> wrote:
> Dear All,
>
> I have qualify the PQR using proposed wps Process are GTAW/SMAW/SAW.
> After all NDT & DT completed on same and actual WPS prepared and production
> weld also done using that WPS with same welding process.
>
> Now my production dept want to rewrite the WPS using only GTAW & SAW due to
> repairs on production welds. Because repairs are @ SMAW weld location.
>
> QW-200.4 is permitting this?
>
> Thank you,
> Regards,
> S.Senthilkumar
>
>
>
> Your Mail works best with the New Yahoo Optimized IE8. Get it NOW!
> http://downloads.yahoo.com/in/internetexplorer/
>
> --
> To post to this group, send email to materials-welding@googlegroups.com
> To unsubscribe from this group, send email to
> materials-welding-unsubscribe@googlegroups.com
> For more options, visit this group's bolg at
> http://materials-welding.blogspot.com/
> The views expressed/exchnaged in this group are members personel views and
> meant for educational purposes only, Users must take their own decisions
> w.r.t. applicable code/standard/contract documents.
>
--
Sukamal
--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
No comments:
Post a Comment