[MW:4599] Hydrotest Duration for HDPE U/G Piping

Dear Members,

We are doing HDPE U/G Piping. We want to do the Hydro test this line, as per client spec testing shall be conducted as per the requirement of ASTM F2164. But I don't have this Spec. to verify the test pressure  and holding period.
 
Also as per client spec testing duration including the time required to pressurizing, Stabilizing, holding the test pressure and the depressurization shall not exceed 8hrs. I think this test duration for pipeline not for piping. So I would like to know as per Code ASTM F2164 what is the test pressure and Holding period.


--
With Thanks & Regards,

Mohan, Q8.

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
 
To unsubscribe from this group, send email to materials-welding+unsubscribegooglegroups.com or reply to this email with the words "REMOVE ME" as the subject.

No comments:

[MW:34919] Welder qualification certificate

Dear All     anyone can share a format for welder certificate and card format        Thanks & Best Regards Saleem manhappulath Mob:+9665...