Wednesday, September 30, 2015

Re: [MW:23621] Regarding RT before or after PWHT

Dear ,

Pwht is most important after welding but not for the all line .
Why because we have to identify the changes occur during welding and ...so on so many reasons.

pravez Alam
TP verifier
Air Energy
indonesia
+6289503908946

Expect the Unexpected.....

On Sep 29, 2015 11:37 AM, "Ajay" <donsaab3@gmail.com> wrote:
Dear Sir,

As we all aware that PWHT and RT both are different in nature, in general we perform RT after PWHT(Where PWHT is required to be perform after welding). 

However it is not written anywhere that RT is to be performed after PWHT only.

My question now is , can we perform RT first and then go for PWHT? will it be acceptable ????.
I have seen many client inspectors asked contractors to perform PWHT first then RT whereas their specifications does not say anything in this regard.

All experts are requested to throw light on the subject. Documented proof/literature , if any, to support this will be higly appreciable.



regards,

Ajay 


--
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAM6T1-EGdHb%3DKoxGb-OuLZr5Dr8KpP7_dLG72WQ6AaUdJ-XG-w%40mail.gmail.com.
For more options, visit https://groups.google.com/d/optout.

--
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CALGsPj6HDgAMo8EPwj2bNt%2BuojyzA614GMnMTX7Dxi5D9ZHung%40mail.gmail.com.
For more options, visit https://groups.google.com/d/optout.

No comments:

Re: [MW:35289] Welding consumable for S355J2WP material

S355 J2 WP  is a weathering structural steel  It has better atmospheric corrosion resistance. Use E 8018 - W1/W2  Electrodes This is regular...