Skip to main content

Re: [MW:23593] Regarding RT before or after PWHT

Dear Friends,,,

ASME Code VIII Div 1 is not specifying any NDE just because our vessel
must be subjected to the PWHT.

After completion of each weld unit, the required NDE must be done so
if the work was unsatisfactory then corrective steps can be taken to
improve the welding in the subsequent units.

So either our vessel is subjected to PWHT or not subjected, there is
no differences in the NDE technique and scope.

If our vessel is subjected in spot or full radiography and also PWHT
is mandatory. We must do radiography when welding completed and all
probable defects removed, repaired and reradiographed, then it is the
time to send the vessel to PWHT shop.

I have seen personally some vessel which had been cracked in weld or
even in base metal after PWHT and I understand why you are concern,
but ASME Code has not mandated radiography after PWHT.

So you may ask why code has not mandated this. It might because we
have another check point in hydrostatic testing so any crack which
developed in PWHT most probably will fail in the hydrostatic testing.

We do not must forget, based the ASME code the full responsibility for
pressure vessel is on the shoulder of manufacture not purchaser or
other parties.

You may note before start of the fabrication, the manufacture provided
his WPS and PQR, so if all welding controlled properly based WPS, this
cracking must not be happen.

I have seen some pressure vessel inspections and test plan which the
purchaser mandated RT before and after PWHT, so definitely the
manufacture will charge the purchaser because this is not code
requirement.

I have also seen some pressure vessel purchasers stated this
requirement in their purchase order and manufacture know from first
day of fabrication which has to do two times radiography.

I believe this practice is not correct in pressure vessel inspections,
the manufacture is responsible for quality on his own work and this
responsibility must not be transferred to the purchaser, engineering
companies and etc.

If the pressure vessel failed under hydrostatic test, then manufacture
must make repair or even rebuild the vessel.

So to prevent this bad incident, the manufacture will make all effort
to control the welding process precisely.

thanks,
Balamurugan M,



On 9/29/15, Ajay <donsaab3@gmail.com> wrote:
> Dear Sir,
>
> As we all aware that PWHT and RT both are different in nature, in general
> we perform RT after PWHT(Where PWHT is required to be perform after
> welding).
>
> However it is not written anywhere that RT is to be performed after PWHT
> only.
>
> My question now is , can we perform RT first and then go for PWHT? will it
> be acceptable ????.
> I have seen many client inspectors asked contractors to perform PWHT first
> then RT whereas their specifications does not say anything in this regard.
>
> All experts are requested to throw light on the subject. Documented
> proof/literature , if any, to support this will be higly appreciable.
>
>
>
> regards,
>
> Ajay
>
> --
> You received this message because you are subscribed to the Google Groups
> "Materials & Welding" group.
> To unsubscribe from this group and stop receiving emails from it, send an
> email to materials-welding+unsubscribe@googlegroups.com.
> To post to this group, send email to materials-welding@googlegroups.com.
> Visit this group at http://groups.google.com/group/materials-welding.
> To view this discussion on the web visit
> https://groups.google.com/d/msgid/materials-welding/CAM6T1-EGdHb%3DKoxGb-OuLZr5Dr8KpP7_dLG72WQ6AaUdJ-XG-w%40mail.gmail.com.
> For more options, visit https://groups.google.com/d/optout.
>

--
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAL9C6DbE5rJd_30WhrgwbU9CKxG5F8WfCbd0r8NTYKmKdwsJsA%40mail.gmail.com.
For more options, visit https://groups.google.com/d/optout.

Comments

Popular posts from this blog

Materails FAQs

Q: What are equivalents for standard Q 235 B (and Q 235 A) for U-channels? (asked by: boris.vielhaber@vait.com) A: DIN Nr. = 2393 T.2, 2394 T.2, EN 10025 W. Nr. DIN 17007 = 1.0038 Design DIN 17006 = RSt 37-2, S235JRG2 (Fe 360 B) Q: What is St DIN 2391 BK material? (asked by: dmcandrews@automaticstamp.com) A: Precision steel tubes, cold-finished/hard. Q: What is C.D.W. Boiler Tube? (asked by: montydude123@yahoo.com) A: Cold Drawn Welded Boiler Tube. Q: WHAT IS W.Nr. 1.4301? PLS TELL US IN EASY LANGUAGUE (asked...

Heat tint (temper) colours on stainless steel surfaces heated in air // Heat tint

Introduction The colour formed when stainless steel is heated, either in a furnace application or in the heat affected zone of welds, is dependent on several factors that are related to the oxidation resistance of the steel. The heat tint or temper colour formed is caused by the progressive thickening of the surface oxide layer and so, as temperature is increased, the colours change.   Oxidation resistance of stainless steels However, there are several factors that affect the degree of colour change and so there is no a single table of colour and temperature that represents all cases. The colours formed can only be used as an indication of the temperature to which the steel has been heated. Factors affecting the heat tint colours formed Steel composition The chromium content is the most important single factor affecting oxidation resistance. The higher the chromium, the more heat resistant the steel and so the development of the heat tint colou...

Re: [MW:10788] ON PLOT PIPING & OFF PLOT PIPING

Piping systems involved for the flow lines and gathering lines from the well head isolation valve to the production facility or processing plant isolation valve are determined as OFF PLOT. ON PLOT defines piping system in the processing plant and production platform. ANSI/ASME B31.4 applies for off plot piping system. B31.4 allows the use of either API 1104 or ASME section IX (as appropriate). However, occasionally, a very small system such as piping within 500 feet of a processing plant (some client also said 400 feet) may be declared B31.3 rather than B31.4. When B31.3 is invoked, only ASME Section IX is used. before you decide which code to use for welding procedure and/or welder qualification for pipe welding, you have to know the design and construction code applicable to the system. Please read far enough into scope and diagram illustrating the application of either B31.3 and B31.4 hope this helps rgds 2011/4/21 pradip kumar sil < pradipsil@gmail.com > Dear all, ...