true because of sensitization
but the image of the vessel indicates iron contamination
best regards
Dr. Georgios Dilintas
Authorized Nuclear Inspector
Authorized Inspector Supervisor
I&F REGIONAL TECHNICAL MANAGER
BUREAU VERITAS PIRAEUS - GREECE
Tel: +30 210 40 63 113 /4 /5
Fax: +30 210 40 63 118
Cell: +30 69 44 64 62 04
This message contains confidential information. To know more, please click on the following link: http://disclaimer.bureauveritas.com
Wednesday, September 30, 2015
RE: [MW:23631] RE: 23626] Re: NEED ADVISE CORROSION IN INHIBITOR TANK REGD
RE: [MW:23630] RE: 23626] Re: NEED ADVISE CORROSION IN INHIBITOR TANK REGD
I definitely agree with the below statement.
From corrosion testing we have performed on 316L and 2101 duplex the HAZ on these welds are very prone to pitting and crevice corrosion due to austenite and ferrite balance.
Heat input is critical.
The elevated temperatures are definitely a factor in the corrosion equation.
With the environment carbon pickup is definitely a factor.
From: materials-welding@googlegroups.com [mailto:materials-welding@googlegroups.com] On Behalf Of Alan Denney
Sent: Wednesday, September 30, 2015 6:44 AM
To: materials-welding@googlegroups.com
Subject: [MW:23629] RE: 23626] Re: NEED ADVISE CORROSION IN INHIBITOR TANK REGD
In my view it comes down to understanding the environment in which the material is to be exposed, (marine and high temperature relative to CPT) and the limitations of 316 stainless steel. There is a lot of information on the web if you do a search. The material selection is hence wrong for the external environment, or the tank should have been painted – yes you do paint stainless steel!
Alan Denney
AKD Materials Consulting Ltd
From: materials-welding@googlegroups.com [mailto:materials-welding@googlegroups.com]
Sent: 30 September 2015 10:55
To: pgoswami <pgoswami@quickclic.net>
Cc: <materials-welding@googlegroups.com> <materials-welding@googlegroups.com>
Subject: [MW:23626] Re: NEED ADVISE CORROSION IN INHIBITOR TANK REGD
Dear Sir,
It's is a corrosion inhibitor storage tank for subsea pipeline project ,
operating temperature is 40degree Celsius ,
Operating pressure. Is .7KPA
Chemical is injected inside the tank , as per design data sheet there is no insulation.
Now I have planned to visit the location and provide more information in environmental condition,
Almost 5years completed and dispatched the job.
P.NEILASHKUMAR
Sent from my iPad
MOB : 966 533098265
91+9952110791
On Sep 30, 2015, at 5:27 AM, pgoswami <pgoswami@quickclic.net> wrote:
Hi Neileshkumar,
What're the surrounding operating or environmental conditions around the tank. Are there any acid fumes involved. Looks like this tank was not insulated at all??? Is that true.
Appreciate more information on the operating conditions.
Thanks
Pradip Goswami, P.Eng,IWE
Welding & Metallurgical Engineering Specialist
Hamilton, Ontario, Canada
pgoswami@quickclic.net
pradip.goswami@gmail.com
ca.linkedin.com/pub/pradip-goswami/5/985/299
-----Original Message-----
From: Neilash Kumar [mailto:neilashkumar@yahoo.com]
Sent: Tuesday, September 29, 2015 2:45 AM
To: Pgosami Sir; Pgosami sir
Subject: NEED ADVISE CORROSION IN INHIBITOR TANK REGD
Dear Sir,
Good Morning, please find the attached tank drawing fabricated by us for our client & it is corroded fully , Can you please clarify,
1. Why the tank are corroded So fast?
2. Can you please advise us the method to stop /reduce the rate of corrosion by applying a top coat & what type of coating to be applied?
please advise me . Material is 316L tank.
Regards
P.Neilashkumar
<Tank Corrosion.pdf>
--
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/81B20544-18A9-45D3-81A3-EDB56129B98A%40yahoo.com.
For more options, visit https://groups.google.com/d/optout.
This email has been scanned by BullGuard antivirus protection.
For more info visit www.bullguard.com
--
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/000001d0fb75%243f7b6060%24be722120%24%40denney1.freeserve.co.uk.
For more options, visit https://groups.google.com/d/optout.
[MW:23629] RE: 23626] Re: NEED ADVISE CORROSION IN INHIBITOR TANK REGD
In my view it comes down to understanding the environment in which the material is to be exposed, (marine and high temperature relative to CPT) and the limitations of 316 stainless steel. There is a lot of information on the web if you do a search. The material selection is hence wrong for the external environment, or the tank should have been painted – yes you do paint stainless steel!
Alan Denney
AKD Materials Consulting Ltd
From: materials-welding@googlegroups.com [mailto:materials-welding@googlegroups.com]
Sent: 30 September 2015 10:55
To: pgoswami <pgoswami@quickclic.net>
Cc: <materials-welding@googlegroups.com> <materials-welding@googlegroups.com>
Subject: [MW:23626] Re: NEED ADVISE CORROSION IN INHIBITOR TANK REGD
Dear Sir,
It's is a corrosion inhibitor storage tank for subsea pipeline project ,
operating temperature is 40degree Celsius ,
Operating pressure. Is .7KPA
Chemical is injected inside the tank , as per design data sheet there is no insulation.
Now I have planned to visit the location and provide more information in environmental condition,
Almost 5years completed and dispatched the job.
P.NEILASHKUMAR
Sent from my iPad
MOB : 966 533098265
91+9952110791
On Sep 30, 2015, at 5:27 AM, pgoswami <pgoswami@quickclic.net> wrote:
Hi Neileshkumar,
What're the surrounding operating or environmental conditions around the tank. Are there any acid fumes involved. Looks like this tank was not insulated at all??? Is that true.
Appreciate more information on the operating conditions.
Thanks
Pradip Goswami, P.Eng,IWE
Welding & Metallurgical Engineering Specialist
Hamilton, Ontario, Canada
pgoswami@quickclic.net
pradip.goswami@gmail.com
ca.linkedin.com/pub/pradip-goswami/5/985/299
-----Original Message-----
From: Neilash Kumar [mailto:neilashkumar@yahoo.com]
Sent: Tuesday, September 29, 2015 2:45 AM
To: Pgosami Sir; Pgosami sir
Subject: NEED ADVISE CORROSION IN INHIBITOR TANK REGD
Dear Sir,
Good Morning, please find the attached tank drawing fabricated by us for our client & it is corroded fully , Can you please clarify,
1. Why the tank are corroded So fast?
2. Can you please advise us the method to stop /reduce the rate of corrosion by applying a top coat & what type of coating to be applied?
please advise me . Material is 316L tank.
Regards
P.Neilashkumar
<Tank Corrosion.pdf>
--
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/81B20544-18A9-45D3-81A3-EDB56129B98A%40yahoo.com.
For more options, visit https://groups.google.com/d/optout.
Re: [MW:23628] Filler wire for EN 10088-2 X2CrNiN18-7 for (MAG -135 welding process)
What is the AWS classification & UTS value of it?Thank youVijay KatkarOn Tue, Sep 29, 2015 at 2:31 PM, Raghuram Bathula <raghurambathula@gmail.com> wrote:Why not with NiCrMo type?On 29 September 2015 at 12:35, Vijay Katkar <katkar.vijay22@gmail.com> wrote:Dear All,Need your guidance on subjected topic.I need filler which will be use to weld X2CrNiN18-7 material (equivalent ASTM material 301NL (Which has 550 MPa minimum tensile requirement).Generally we use ER 308L material to weld this material but as per EN 10088-2, we need minimum tensile value 650MPa.Tensile value for Filler wire- ER 308L is 520MPa minimum.We have some PQR which is less than 650 MPA, so it can not be use.I checked Filler wire MTC which has 610 MPa tensile value (less than requirement).So which filler wire can be suitable to weld this material.Please provide your valuable reply.Thank youVijay Katkar-
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CADxVubnJPzUBvK5oNg0hGjv4zJ9TTV61dM_MaieCy3pF8nH5-w%40mail.gmail.com.
For more options, visit https://groups.google.com/d/optout.
Re: [MW:23627] Filler wire for EN 10088-2 X2CrNiN18-7 for (MAG -135 welding process)
Why not with NiCrMo type?--On 29 September 2015 at 12:35, Vijay Katkar <katkar.vijay22@gmail.com> wrote:Dear All,Need your guidance on subjected topic.I need filler which will be use to weld X2CrNiN18-7 material (equivalent ASTM material 301NL (Which has 550 MPa minimum tensile requirement).Generally we use ER 308L material to weld this material but as per EN 10088-2, we need minimum tensile value 650MPa.Tensile value for Filler wire- ER 308L is 520MPa minimum.We have some PQR which is less than 650 MPA, so it can not be use.I checked Filler wire MTC which has 610 MPa tensile value (less than requirement).So which filler wire can be suitable to weld this material.Please provide your valuable reply.Thank youVijay Katkar
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CADxVub%3DJhdMLghkvctJk%2BrcuK_e9WEYs2eSy_uecaAt6-ihPfA%40mail.gmail.com.
For more options, visit https://groups.google.com/d/optout.
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAP37wrKf2k0af2sxjCzmSGdJ7y%3DQco1vMv7afjjTZ9wHRLRF-Q%40mail.gmail.com.
For more options, visit https://groups.google.com/d/optout.
[MW:23626] Re: NEED ADVISE CORROSION IN INHIBITOR TANK REGD
P.NEILASHKUMAR
Hi Neileshkumar,
What're the surrounding operating or environmental conditions around the tank. Are there any acid fumes involved. Looks like this tank was not insulated at all??? Is that true.
Appreciate more information on the operating conditions.
Thanks
Pradip Goswami, P.Eng,IWE
Welding & Metallurgical Engineering Specialist
Hamilton, Ontario, Canada
pgoswami@quickclic.net
pradip.goswami@gmail.com
ca.linkedin.com/pub/pradip-goswami/5/985/299
-----Original Message-----
From: Neilash Kumar [mailto:neilashkumar@yahoo.com]
Sent: Tuesday, September 29, 2015 2:45 AM
To: Pgosami Sir; Pgosami sir
Subject: NEED ADVISE CORROSION IN INHIBITOR TANK REGD
Dear Sir,
Good Morning, please find the attached tank drawing fabricated by us for our client & it is corroded fully , Can you please clarify,
1. Why the tank are corroded So fast?
2. Can you please advise us the method to stop /reduce the rate of corrosion by applying a top coat & what type of coating to be applied?
please advise me . Material is 316L tank.
Regards
P.Neilashkumar
<Tank Corrosion.pdf>
Re: [MW:23625] Electrode Qualification Test requirement
From: mohan raj v <vmraj2001@gmail.com>
To: Materials & Welding <materials-welding@googlegroups.com>
Sent: Tuesday, September 29, 2015 11:34 PM
Subject: [MW:23618] Electrode Qualification Test requirement
Please clarify for electrode qualification test as per ASME Sec II Part C for E7018 Dia-4 mm, what are the test requirements?.
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/021aa57f-3ee7-4f7f-98f5-e43c1122d570%40googlegroups.com.
For more options, visit https://groups.google.com/d/optout.
Re: [MW:23624] Regarding RT before or after PWHT
The reason for pwht is to get rid of hydrogen cracking.......ask yourself.....is hydrogen cracking a planar defect or a volumner defect.....if its planar then you can do a rt before pwht but if the defects in hydrogen cracking is volumner too then you cant do a pwht.....
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAHJeEXG9sh5EukDknY3Vagj%3DuowWHBFoEMbyud2Wp0x1fTOZ5g%40mail.gmail.com.On 30 Sep 2015 13:10, "Himan Nikdin" <himan.nikdin@outlook.com> wrote:----Hi Everybody
"For P-Nos. 3, 4, and 5 materials, examination shall be performed after completion of any heat treatment" this phrase is from ANSI B31.3 para 341.3(a) Examination Requirements.
Regards,
H.Nikdin
To: materials-welding@googlegroups.com
Date: Tue, 29 Sep 2015 07:29:37 +0200
From: george.dilintas@gr.bureauveritas.com
Subject: Re: [MW:23580] Regarding RT before or after PWHT
As a rule NDT has to be performed after all fabrication steps including PWHT. Some codes allow exceptionsSent from my BlackBerry 10 smartphone.
From: AjaySent: Τρίτη, 29 Σεπτεμβρίου 2015 - 07:37Reply To: materials-welding@googlegroups.comSubject: [MW:23575] Regarding RT before or after PWHTThis message contains confidential information. To know more, please click on the following link: http://disclaimer.bureauveritas.comDear Sir,As we all aware that PWHT and RT both are different in nature, in general we perform RT after PWHT(Where PWHT is required to be perform after welding).However it is not written anywhere that RT is to be performed after PWHT only.My question now is , can we perform RT first and then go for PWHT? will it be acceptable ????.I have seen many client inspectors asked contractors to perform PWHT first then RT whereas their specifications does not say anything in this regard.All experts are requested to throw light on the subject. Documented proof/literature , if any, to support this will be higly appreciable.regards,Ajay
--
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAM6T1-EGdHb%3DKoxGb-OuLZr5Dr8KpP7_dLG72WQ6AaUdJ-XG-w%40mail.gmail.com.
For more options, visit https://groups.google.com/d/optout.
--
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/OF9BCA633F.ED3E9828-ONC1257ECF.001E2D43-1443504577147%40LocalDomain.
For more options, visit https://groups.google.com/d/optout.
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/BLU180-W85EB04A828A42BDDCFCF29E4E0%40phx.gbl.
For more options, visit https://groups.google.com/d/optout.
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAM6T1-HRC1CwcAhohojf1s1haomxbwo2CxMMHnF9_ekw4aDuUA%40mail.gmail.com.
For more options, visit https://groups.google.com/d/optout.
RE: [MW:23623] Regarding RT before or after PWHT
Date: Wed, 30 Sep 2015 13:17:07 +0900
Subject: RE: [MW:23621] Regarding RT before or after PWHT
From: salman96996@gmail.com
To: materials-welding@googlegroups.com
The reason for pwht is to get rid of hydrogen cracking.......ask yourself.....is hydrogen cracking a planar defect or a volumner defect.....if its planar then you can do a rt before pwht but if the defects in hydrogen cracking is volumner too then you cant do a pwht.....
Hi Everybody
"For P-Nos. 3, 4, and 5 materials, examination shall be performed after completion of any heat treatment" this phrase is from ANSI B31.3 para 341.3(a) Examination Requirements.
Regards,
H.Nikdin
To: materials-welding@googlegroups.com
Date: Tue, 29 Sep 2015 07:29:37 +0200
From: george.dilintas@gr.bureauveritas.com
Subject: Re: [MW:23580] Regarding RT before or after PWHT
As a rule NDT has to be performed after all fabrication steps including PWHT. Some codes allow exceptionsSent from my BlackBerry 10 smartphone.
From: AjaySent: Τρίτη, 29 Σεπτεμβρίου 2015 - 07:37Reply To: materials-welding@googlegroups.comSubject: [MW:23575] Regarding RT before or after PWHTThis message contains confidential information. To know more, please click on the following link: http://disclaimer.bureauveritas.comDear Sir,As we all aware that PWHT and RT both are different in nature, in general we perform RT after PWHT(Where PWHT is required to be perform after welding).However it is not written anywhere that RT is to be performed after PWHT only.My question now is , can we perform RT first and then go for PWHT? will it be acceptable ????.I have seen many client inspectors asked contractors to perform PWHT first then RT whereas their specifications does not say anything in this regard.All experts are requested to throw light on the subject. Documented proof/literature , if any, to support this will be higly appreciable.regards,Ajay
--
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAM6T1-EGdHb%3DKoxGb-OuLZr5Dr8KpP7_dLG72WQ6AaUdJ-XG-w%40mail.gmail.com.
For more options, visit https://groups.google.com/d/optout.
--
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/OF9BCA633F.ED3E9828-ONC1257ECF.001E2D43-1443504577147%40LocalDomain.
For more options, visit https://groups.google.com/d/optout.
--
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/BLU180-W85EB04A828A42BDDCFCF29E4E0%40phx.gbl.
For more options, visit https://groups.google.com/d/optout.
--
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAHJeEXG9sh5EukDknY3Vagj%3DuowWHBFoEMbyud2Wp0x1fTOZ5g%40mail.gmail.com.
For more options, visit https://groups.google.com/d/optout.
Re: [MW:23621] Regarding RT before or after PWHT
Dear ,
Pwht is most important after welding but not for the all line .
Why because we have to identify the changes occur during welding and ...so on so many reasons.
pravez Alam
TP verifier
Air Energy
indonesia
+6289503908946
Expect the Unexpected.....
Dear Sir,--As we all aware that PWHT and RT both are different in nature, in general we perform RT after PWHT(Where PWHT is required to be perform after welding).However it is not written anywhere that RT is to be performed after PWHT only.My question now is , can we perform RT first and then go for PWHT? will it be acceptable ????.I have seen many client inspectors asked contractors to perform PWHT first then RT whereas their specifications does not say anything in this regard.All experts are requested to throw light on the subject. Documented proof/literature , if any, to support this will be higly appreciable.regards,Ajay
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAM6T1-EGdHb%3DKoxGb-OuLZr5Dr8KpP7_dLG72WQ6AaUdJ-XG-w%40mail.gmail.com.
For more options, visit https://groups.google.com/d/optout.
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CALGsPj6HDgAMo8EPwj2bNt%2BuojyzA614GMnMTX7Dxi5D9ZHung%40mail.gmail.com.
For more options, visit https://groups.google.com/d/optout.
RE: [MW:23621] Regarding RT before or after PWHT
The reason for pwht is to get rid of hydrogen cracking.......ask yourself.....is hydrogen cracking a planar defect or a volumner defect.....if its planar then you can do a rt before pwht but if the defects in hydrogen cracking is volumner too then you cant do a pwht.....
--Hi Everybody
"For P-Nos. 3, 4, and 5 materials, examination shall be performed after completion of any heat treatment" this phrase is from ANSI B31.3 para 341.3(a) Examination Requirements.
Regards,
H.Nikdin
To: materials-welding@googlegroups.com
Date: Tue, 29 Sep 2015 07:29:37 +0200
From: george.dilintas@gr.bureauveritas.com
Subject: Re: [MW:23580] Regarding RT before or after PWHT
As a rule NDT has to be performed after all fabrication steps including PWHT. Some codes allow exceptionsSent from my BlackBerry 10 smartphone.
From: AjaySent: Τρίτη, 29 Σεπτεμβρίου 2015 - 07:37Reply To: materials-welding@googlegroups.comSubject: [MW:23575] Regarding RT before or after PWHTThis message contains confidential information. To know more, please click on the following link: http://disclaimer.bureauveritas.comDear Sir,As we all aware that PWHT and RT both are different in nature, in general we perform RT after PWHT(Where PWHT is required to be perform after welding).However it is not written anywhere that RT is to be performed after PWHT only.My question now is , can we perform RT first and then go for PWHT? will it be acceptable ????.I have seen many client inspectors asked contractors to perform PWHT first then RT whereas their specifications does not say anything in this regard.All experts are requested to throw light on the subject. Documented proof/literature , if any, to support this will be higly appreciable.regards,Ajay
--
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAM6T1-EGdHb%3DKoxGb-OuLZr5Dr8KpP7_dLG72WQ6AaUdJ-XG-w%40mail.gmail.com.
For more options, visit https://groups.google.com/d/optout.
--
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/OF9BCA633F.ED3E9828-ONC1257ECF.001E2D43-1443504577147%40LocalDomain.
For more options, visit https://groups.google.com/d/optout.
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/BLU180-W85EB04A828A42BDDCFCF29E4E0%40phx.gbl.
For more options, visit https://groups.google.com/d/optout.
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAHJeEXG9sh5EukDknY3Vagj%3DuowWHBFoEMbyud2Wp0x1fTOZ5g%40mail.gmail.com.
For more options, visit https://groups.google.com/d/optout.
[MW:23613] FW: NEED ADVISE CORROSION IN INHIBITOR TANK REGD
Hi Neileshkumar,
What're the surrounding operating or environmental conditions around the tank. Are there any acid fumes involved. Looks like this tank was not insulated at all??? Is that true.
Appreciate more information on the operating conditions.
Pradip Goswami, P.Eng,IWE
Welding & Metallurgical Engineering Specialist
Hamilton, Ontario, Canada
pgoswami@quickclic.net
pradip.goswami@gmail.com
ca.linkedin.com/pub/pradip-goswami/5/985/299
-----Original Message-----
From: Neilash Kumar [mailto:neilashkumar@yahoo.com]
Sent: Tuesday, September 29, 2015 2:45 AM
To: Pgosami Sir; Pgosami sir
Subject: NEED ADVISE CORROSION IN INHIBITOR TANK REGD
Dear Sir,
Good Morning, please find the attached tank drawing fabricated by us for our client & it is corroded fully , Can you please clarify,
1. Why the tank are corroded So fast?
2. Can you please advise us the method to stop /reduce the rate of corrosion by applying a top coat & what type of coating to be applied?
please advise me . Material is 316L tank.
Regards
P.Neilashkumar
[MW:23612] MW:23607]-Impact test requirements of UNS 31254 as per B31.3
Hi,Mohammed Azharuddin,
As per B-31.3, UNS S 31254 is allowed for design condition up to -325 Deg F(-196 Deg C) , with the specified material properties mentioned as below(See A-1). In addition the base metal should be solution annealed.
Theoretically as per Table -323.2.2, austenitic stainless steel welds would require impact testing if the conditions mentioned below are not fulfilled.
One has to know the the procurement specification for UNS 31254 pipe???
If the pipes are impact tested in the mills @ -325 DegF then it's deemed that subject to good welding condition and subject to the good impact values of the welding consumables (same as base metal) , impact test would be exempted in the weld coupons @ -120 Deg C. Also all the clauses in Table 323.2.2 needs to be fulfilled
However the integrity of UNS S31254 is a crucial factor in any offshore application (I assume it's the intended use).
If that's the case I would advise the impact to be done on the procedure qualification coupon for due diligence.
Thanks.
Pradip Goswami, P.Eng,IWE
Welding & Metallurgical Engineering Specialist
Hamilton, Ontario, Canada
pgoswami@quickclic.net
pradip.goswami@gmail.com
ca.linkedin.com/pub/pradip-goswami/5/985/299
A-2
-----Original Message-----
From: materials-welding@googlegroups.com [mailto:materials-welding@googlegroups.com]
Sent: Tuesday, September 29, 2015 10:58 AM
To: materials-welding@googlegroups.com
Subject: [MW:23607] Impact test requirements of UNS 31254 as per B31.3
Dear Experts,
I have to qualify a welding procedure for welding of UNS 31254 base metals.My design temperature is -120 degree centigrade.I am using ERNiCrMo-3 filler wire.Please advice if Impact test is required to be performed at min.design temperature?
Base metal : UNS 31254
Filler : ERNiCrMo-3
Design Temperature : -120 deg.centigrade Thickness : 5.54 & 15.54 (2 PQRS) Code : ASME B31.3
Thanks a lot
Regards,
Mohammed Azharuddin
--
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/1443538702.54688.YahooMailBasic%40web193205.mail.sg3.yahoo.com.
For more options, visit https://groups.google.com/d/optout
Re: [MW:23614] RE: 23575] Regarding RT before or after PWHT
Yes P15E very much.
--P-No 15E included. Example P91. For the other Pnos the Engineering has to agree for the PWHT timing. Check closer in B31.1Sent from my BlackBerry 10 smartphone.
From: Kannayeram GnanapandithanSent: Τρίτη, 29 Σεπτεμβρίου 2015 - 16:47To: materials-weldingReply To: materials-welding@googlegroups.comSubject: Re: [MW:23605] RE: 23575] Regarding RT before or after PWHTThis message contains confidential information. To know more, please click on the following link: http://disclaimer.bureauveritas.comref B31.1, 136.4, NDE of P3,4 &5A and 5B materials welds shall be performed after PWHT. For other materials , NDE may be before or after PWHT--THANKS & BEST REGARDS,KG.PANDITHAN, IWE, AWS-CWI, CSWIP 3.1,CONSULTANT-WELDING & QUALITYOn Tue, Sep 29, 2015 at 1:40 PM, Ajay <donsaab3@gmail.com> wrote:Dear Sir,I do agree with u completely,,,,,,,,,,,,But many contractors adament to do RT after PWHT.......if any documents to support the statement would be highly appreciated.To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAM6T1-F-ZVH%3DT6iweXK0etBbsiNr%3DvTt-1%2Bhu%2BYAfC%3DXin1UYw%40mail.gmail.com.--On Tue, Sep 29, 2015 at 1:33 PM, Alan Denney <alan@denney1.freeserve.co.uk> wrote:PWHT will relieve residual stress and can open up flaws which are otherwise closed by the residual stresses, and that is the reason why NDT for acceptance purposes is performed after PWHT.
Alan Denney
AKD Materials Consulting Ltd
From: materials-welding@googlegroups.com [mailto:materials-welding@googlegroups.com] On Behalf Of Ajay
Sent: 29 September 2015 05:03
To: materials-welding@googlegroups.com
Subject: [MW:23575] Regarding RT before or after PWHT
Dear Sir,
As we all aware that PWHT and RT both are different in nature, in general we perform RT after PWHT(Where PWHT is required to be perform after welding).
However it is not written anywhere that RT is to be performed after PWHT only.
My question now is , can we perform RT first and then go for PWHT? will it be acceptable ????.
I have seen many client inspectors asked contractors to perform PWHT first then RT whereas their specifications does not say anything in this regard.
All experts are requested to throw light on the subject. Documented proof/literature , if any, to support this will be higly appreciable.
regards,
Ajay
--
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAM6T1-EGdHb%3DKoxGb-OuLZr5Dr8KpP7_dLG72WQ6AaUdJ-XG-w%40mail.gmail.com.
For more options, visit https://groups.google.com/d/optout.This email has been scanned by BullGuard antivirus protection.For more info visit www.bullguard.com--
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/004101d0fa8d%245f012e30%241d038a90%24%40denney1.freeserve.co.uk.
For more options, visit https://groups.google.com/d/optout.
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAJzm4ePp43i7ks%2BqKtkdFXo3cXDJw-77i5KGTk1xxWyTjR%2B85Q%40mail.gmail.com.
For more options, visit https://groups.google.com/d/optout.
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/OFB4537794.0A439131-ONC1257ECF.0052ACE2-1443538982310%40LocalDomain.
For more options, visit https://groups.google.com/d/optout.
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAJzm4eNh2EWVyThGSf279S%3Db5q3zeoAPAYRUU5MMMqwXYbkEaA%40mail.gmail.com.
For more options, visit https://groups.google.com/d/optout.
[MW:35346] Cast-iron welding
Any advice for cast iron welding Sent from Yahoo Mail for iPhone
-
Q: What are equivalents for standard Q 235 B (and Q 235 A) for U-channels? ...
-
Definition of buttering from ASME Section IX, QW/QB-492 Definitions: Buttering: the addition of material, by welding, on one or bot...
-
Section I. PRINT READING 3-1. GENERAL a. Drawings . Drawing or sketching is a universal language used to convey all necessary information to...