I have 1 question for you
We had finished the hydrotesting of the pump station. But now electric
company ask for adding 1 pipe (2 inch) to a 40" pipe. But we have
already finished the hydrotest for this line. I need to know does
anyone know any standard or specification that tells any solution for
this sitaution except re-hydortesting.
Thanks for kind attention
--