Tuesday, October 25, 2011

[SUSPECTED SPAM] Re: [MW:12766] DFT ACCEPTANCE AND REJECTION OF PAINTING.

Dear friend,
 As all related are well known about painting as far as my knowledge if your requirement is 75 microns you have to maintained DFT  through out the job but; practically it is not possible to maintained DFT uniformaly.however   must be try to maintained DFT as required  but avarage DFT is not a solution to
accept the painting because suppose you observed 25, 40, 50  etc.  microns in place of 75 mirons you must  checked surrounding painted area's DFT and according to that you must be re-work to maintain Required DFT if it is less than required .  In the meanwhile prior to apply paint you must check the retio of mixing /pressure/distance . which may help you to maintained DFT near about or  pluss side of requirement but .".AVERAGE DFT IS NOT A SOLUTION TO ACCEPT THE PAINTING.

Regard,
RK Vichare



--- Original Message -----

From: manoj john

To: materials-welding@googlegroups.com

Sent: Mon, 3 Oct 2011 09:07:13 +0530 (IST)

Subject: [MW:12607] DFT ACCEPTANCE AND REJECTION OF PAINTING.



Dear All,
Can anybody give the acceptance and rejection criteria as per SSPC PA2.  I have applied primer to the shell surface of storage tank.  The minimum DFT required is 75 micron.  The actual average DFT is  70 micron and above but at some spot I got 15, 30 , 40 microns. Is it acceptable the total area is  2500 M2.



I have taken 5 spot reading in 100 Sqft and each spot is the average of three single reading, in the single reading i am getting 15, 30, 40 microns but average spot reading is above 70 microns. 



Thanks in advance 
Manoj John.








--


To post to this group, send email to materials-welding@googlegroups.com


To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com


For more options, visit this group's bolg at http://materials-welding.blogspot.com/


The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

Re: [MW:34913] Filler wire

E71T-1C  is Charpy Impact tested at -20degC E71T-1CJ is Charpy impact tested at -40degC. AWS Classification for FCAW is only a supplementary...