DEAR EXPERTS PL. RESPOND:
AS PER  UCS79 OF ASME SEC. VIII DIV. HEAT TREATMENT IS REQUIRED AFTER PERCENTAGE ELONGATION OF FORMED COMPONENTS EXCEEDS SPECIFIED LIMIT.
 WHETHER THE HEAT TREATMENT IS STRESS RELEVING OR WHETHER IT IS NORMALISING?
 
 
 
 

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:34920] Tubesheet Hole step