Dear Bhatti,
 What is code for Procedure? What is the job? Normally you require tensile,bend,charpy impact(conditional) and macroexamination.

2010/6/17 Bhatti BM (Bashir) at Aera <BMBhatti@aeraenergy.com>

 

 

 

Folks,

We doing  Mockup procedure before actual welding, what type tests are required to qualify the welding procedure

 

 I was looking for welding procedures for and filler metals

 CS A-106-B and 2 ¼ Cr ,

CS A-106-B and 410

CS A-106-B and 13 Cr

CS A-106-B and 9CR

 

Thanks , Bashbhat

 

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.



--
K Harish Kumar

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:34920] Tubesheet Hole step

Hello Team, I have one question any tolerance given for tubesheet Hole step. Please do needful. Regards, AP  -- https://materials-...