Many thanks, problem solved. I still had the old 2005 add.

 

Best regards.

 

From: materials-welding@googlegroups.com [mailto:materials-welding@googlegroups.com] On Behalf Of Jorge Mejía Lema
Sent: 11 September 2012 05:58 PM
To: materials-welding@googlegroups.com
Subject: Re: [MW:15275] FW: API 653 'major repair'

 

Dear Riaan Stolz: please see, API 653 Four Edition, April 2009, Section 3, Definitions, Numeral 3.18, c. removing and replacing or adding a shell plate beneath the design liquid level where the lonest dimentio of the replacement plate 12 in.

if you can not like to do a hidrostatic  test please see Numeral 12.3.2 When hydrostatic testing is not requiered.

 Regards,

jml, Colombia, South America

2012/9/11 Riaan Stoltz <Riaan@ritc.co.za>

 

Good day dear experts

 

I have trouble understanding the meaning of “major repair “ as per API 653. 3.23

 

We have done some tank bottom repair work on a fuel tank as per API 653. We had to cut an envelope into the tank shell (300mm x 2000mm) to get the repair plates into the tank. Is it a requirement as per API 653 to carry out a hydrostatic stand test.

The envelope is cut out of the “critical zone” area  and no repairs were done on the tank floor within the ‘critical zone’. Does the envelope constitute a major repair?

 

Your advice would be greatly appreciated.

 

Best regards

 

RIAAN STOLTZ

RITC INSPECTION

083 640 5909

021 556 4884 (TEL)

021 556 6941 (FAX)

 

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
 
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
 
 

 

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
 
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
 
 

No comments:

[MW:34916] Applicability of Impact requirement as per ASME B31.3

Dear All, Design code – ASME B31.3, Welding Code- ASME BPVC SEC IX Material  to be used used during Fabrication - SA 333Gr6 (P No.1 G...