Saturday, September 22, 2012

[MW:15361] Socket weld gap requirement

Dear experts,

As per ASME 3.1.& 31.3 socket weld gap requirement is 1/16" before welding. Whether it is required for after welding, if its require kindly provide the code details.In our project we're done RT for socket welds. But after welding did not find the 1/16" gap, its less than 0.5mm. Our client decision is to cut and reweld the all joints.
 
 
Thanks & Regards,
Naresh

No comments:

Re: [MW:35289] Welding consumable for S355J2WP material

S355 J2 WP  is a weathering structural steel  It has better atmospheric corrosion resistance. Use E 8018 - W1/W2  Electrodes This is regular...