Wednesday, December 28, 2022

Re: [MW:33878] Re: NDT Supplier Assessment

Hi,
NDT contractor.

Regards,
Vivek

On Wed, Dec 28, 2022 at 1:32 PM Mohd Siraj <mohd52100@gmail.com> wrote:
you mean, 

NDT subcontractor or NDT material supplier (vendor)?

On Monday, December 12, 2022 at 5:14:36 PM UTC+3 Vivek wrote:
Dear Members,

For NDT supplier assessment, Do we have any audit format/audit checklist? 

Thank You 
Best Regards
Vivek

--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/91f49aff-6215-4fd8-b30f-2fe58333c8a8n%40googlegroups.com.

--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAHahR6WzVV6He5MCzZBBFq%2B5gHmUdJiEgA_yDJV-q40dHyQvdQ%40mail.gmail.com.

No comments:

[MW:34920] Tubesheet Hole step

Hello Team, I have one question any tolerance given for tubesheet Hole step. Please do needful. Regards, AP  -- https://materials-...