Tuesday, November 10, 2009

[MW:3625] After completion of hydrotest need to do vacuum box?

 Dear All,
 
I am working with API 650, Tenth edition year 2005 for Tank fabrication.
 

Now I want to know that after completion of  hydrotest  is there necessary to do vacuum box on the bottom plate?

If yes, please advice me with code reference. 
 
Thanks in advance,
 
Regards,
Moorthy. 

--~--~---------~--~----~------------~-------~--~----~
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
-~----------~----~----~----~------~----~------~--~---

No comments:

Re: [MW:35374] Material Certification 3.1 / 3.2/2.2--EIL India

Dear Perumal, I answer the same but got one more question where it is written that TPI witness is mandatory? -- https://materials-...