Saturday, April 11, 2009

[MW:1925] equipment alignment tolerance

Hi All,
 
I  have worked 5 project here in middle east as Qc Inspector- mechanical equipment. In all project contractor's QCP is refered for alignment tolerance for verticality and leveling of equipment like column, drums and exchangers. I could not find any reference to this tolerance to international standards or recommended practice. My query is not directly related to welding, but can anybody give name of any standards or RP regarding erection and alignment tolerance for these equipment. (Not fabrication)
 
Thanks and Regards
Ahmed Husain
Borouge2
Abu-Dhabi


--~--~---------~--~----~------------~-------~--~----~
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
-~----------~----~----~----~------~----~------~--~---

No comments:

[MW:34919] Welder qualification certificate

Dear All     anyone can share a format for welder certificate and card format        Thanks & Best Regards Saleem manhappulath Mob:+9665...