Dear Friends As per ASME 3.31.3 gap is given at the time of fit-up and offcurse after weding that gap will be less than 1.5 mm because of shrinkage due to welding heat. the meaning of RT is nothing but radiography test and i think your client might have asked you to perfom Rt to check whether 1.5mm gap has been provided or not not rejected. Regards, Jivan Dhamane --- On Wed, 24/12/08, T. Rizal H. <aatkho@gmail.com> wrote: From: T. Rizal H. <aatkho@gmail.com> |