Refer API 5L for requirments of Spiral welded pipes in pipemill.

 
On 6/2/10, krishna <wiqw@rediffmail.com> wrote:
GUYS,
           Could one brief the requiremnts to be checked for a Spiral welded pipes in pipemill.
SAW pipes is there any weld reinforcement required inside the pipes .
For SAW pipes RT is it not necessary to keep welding operator number in the film?

for Daily One Line Reportis it required to use 2 pressure gauges in hydro testing ?

kk

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.



--
Feroz Mohammed
BV_Vizag
9177631000 begin_of_the_skype_highlighting              9177631000      end_of_the_skype_highlighting

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:34916] Applicability of Impact requirement as per ASME B31.3

Dear All, Design code – ASME B31.3, Welding Code- ASME BPVC SEC IX Material  to be used used during Fabrication - SA 333Gr6 (P No.1 G...