Re: [MW:3754] Re: Pickling and Passivation


Flushing with abundant DM water is essential for cleaning after pickling and passivation.The presence of acid stains can be tested with litmus paper.
regards
M.S.R.K.Srinivasa Prasad
Sr. Manager( Mech. Maint  PP-1)
Nagarjuna Fertilizers And Chemicals
Nagarjuna Road
KAKINADA-533003
Ph: 0884-2360212(O)
                 2379302(R)

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:34916] Applicability of Impact requirement as per ASME B31.3

Dear All, Design code – ASME B31.3, Welding Code- ASME BPVC SEC IX Material  to be used used during Fabrication - SA 333Gr6 (P No.1 G...