It will be available in client specification
On Thu, Jan 9, 2020, 14:39 chiluka venkatramulu <ramuluchiluka@gmail.com> wrote:
Dear All,--Pl clarify whether it is required NDT Level-III approvals for all NDT procedures? or required only for coded vessels.Pl specify the code requirement.Thanks & Regards,Venkatramulu CH
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAF98%2BdHdFX5ePVY4%2B5GB9pFh4ZGGoRu0ntafcZrkCw17XMdkrQ%40mail.gmail.com.
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAPRS9UNDZ1y66%3DxfdmBm0NfKNb6SuPWRVeKi34YiFg2SSu5ONA%40mail.gmail.com.
No comments:
Post a Comment