Skip to main content

[MW:20179] WELDING REALIGNMENT

Dear All,

I would like to seek your opinion, understanding and or feedback with regard to the following question

 

We have a case here where the weld joint required to undergo a repair on a pipe weld due to the radiography taken. There is an approved weld repair procedure which allows us to grind or gouge out the defective area and re-weld with the same approved WPS. This is acceptable to the customer / end user. There is no issue here.

 

However, in another scenario, we discovered some misalignment on the pipe line/ spool during the assembly stage and we grind or gouge part of the weldment and re-weld it back to the correctness or straightness of the line. There is no procedure being submitted in the first place.

We have submitted a NCR and it was accepted by the third party representative but was rejected outright by the end user for failure to provide an approved (re-alignment) procedure and also failed to inform them (customer) in advance prior to any re-work to realign the pipe line (on a gas compressor skid assembly package)   

 

Question :-

1.       Does anyone have any previous experience on what should be carried out for the realignment of the pipe spool or line? Please share.

2.       The customer’s specifications does not clearly indicate this case scenario for further rectification action and  we believe that their specifications does not address this subject, so therefore, it is rejectable by the customer?

3.       Does anyone recall such (experience) issues from the ANSI B31.3 which the pipe spools is based on for the manufacturing and testing?

 

Thank you in advance for sharing with us

 

Thank you

Best Regards

 

David Chan

Singapore

Comments

Popular posts from this blog

Materails FAQs

Q: What are equivalents for standard Q 235 B (and Q 235 A) for U-channels? (asked by: boris.vielhaber@vait.com) A: DIN Nr. = 2393 T.2, 2394 T.2, EN 10025 W. Nr. DIN 17007 = 1.0038 Design DIN 17006 = RSt 37-2, S235JRG2 (Fe 360 B) Q: What is St DIN 2391 BK material? (asked by: dmcandrews@automaticstamp.com) A: Precision steel tubes, cold-finished/hard. Q: What is C.D.W. Boiler Tube? (asked by: montydude123@yahoo.com) A: Cold Drawn Welded Boiler Tube. Q: WHAT IS W.Nr. 1.4301? PLS TELL US IN EASY LANGUAGUE (asked...

Heat tint (temper) colours on stainless steel surfaces heated in air // Heat tint

Introduction The colour formed when stainless steel is heated, either in a furnace application or in the heat affected zone of welds, is dependent on several factors that are related to the oxidation resistance of the steel. The heat tint or temper colour formed is caused by the progressive thickening of the surface oxide layer and so, as temperature is increased, the colours change.   Oxidation resistance of stainless steels However, there are several factors that affect the degree of colour change and so there is no a single table of colour and temperature that represents all cases. The colours formed can only be used as an indication of the temperature to which the steel has been heated. Factors affecting the heat tint colours formed Steel composition The chromium content is the most important single factor affecting oxidation resistance. The higher the chromium, the more heat resistant the steel and so the development of the heat tint colou...

Re: [MW:10788] ON PLOT PIPING & OFF PLOT PIPING

Piping systems involved for the flow lines and gathering lines from the well head isolation valve to the production facility or processing plant isolation valve are determined as OFF PLOT. ON PLOT defines piping system in the processing plant and production platform. ANSI/ASME B31.4 applies for off plot piping system. B31.4 allows the use of either API 1104 or ASME section IX (as appropriate). However, occasionally, a very small system such as piping within 500 feet of a processing plant (some client also said 400 feet) may be declared B31.3 rather than B31.4. When B31.3 is invoked, only ASME Section IX is used. before you decide which code to use for welding procedure and/or welder qualification for pipe welding, you have to know the design and construction code applicable to the system. Please read far enough into scope and diagram illustrating the application of either B31.3 and B31.4 hope this helps rgds 2011/4/21 pradip kumar sil < pradipsil@gmail.com > Dear all, ...