it is always better to understand the thing to avoid safety issue on bursting of system as systems lack of ductility.so it is applicable you
-- reach to working pressure (5 bar / min) then you have to1 bar / min to be in safe sided till your test pressure reached.
regards
dinesh
On Fri, Jul 22, 2011 at 5:16 PM, Shashank Vagal <nach_sam@yahoo.com> wrote:
--Dear members,In hydrotest, if the pressurization rate is required be increased by the mech crew for some reasons, from 1 bar / min to 5 bar / min, what are the implications?Best regards,ShashanK Vagal
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/