[MW:3630] Re: After completion of hydrotest need to do vacuum box?

Hi
we did vacuum test that before hydrotest.......
a tank with hydrostic test finished we consider generally untouchble after that test....\
but if you have doubt or client asked that .....you can do it....
 


 
On Tue, Nov 10, 2009 at 3:52 PM, bdsathiyamoorthy <bdsathiyamoorthy@gmail.com> wrote:
 Dear All,
 
I am working with API 650, Tenth edition year 2005 for Tank fabrication.
 

Now I want to know that after completion of  hydrotest  is there necessary to do vacuum box on the bottom plate?

If yes, please advice me with code reference. 
 
Thanks in advance,
 
Regards,
Moorthy. 





--
Daniel Iordache
Bureau Veritas - Angola
Mechanical& Welding Surveyor
Mobile Ao: +244921544583
Mobile Ro:   +40721731728
E-Mail: daniel.iordache@gmail.com
          daniel_iordache@yahoo.com


--~--~---------~--~----~------------~-------~--~----~
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
-~----------~----~----~----~------~----~------~--~---

No comments:

[MW:34916] Applicability of Impact requirement as per ASME B31.3

Dear All, Design code – ASME B31.3, Welding Code- ASME BPVC SEC IX Material  to be used used during Fabrication - SA 333Gr6 (P No.1 G...