[MW:32015] ASME B31.3 Para 328.2.2 Interpretation

Dear Experts,
Please clarify ASME B31.3 para 328.2.2 Procesure Qualification by Others 
My question is 
Can the Sub Contractor utilized Main / EPC Contractor  WPS for same project?
As per Interpretation number B31.3-18-07
Question (1): In accordance with ASME B31.3-2016, may a contractor follow a WPS that has been qualified by another company in accordance with the requirements of para. 328.2.2?
Reply(1): Yes
Question (2): In accordance with ASME B31.3-2016, does para 328.2.2 take precedence over the rules of ASME Section IX?
Reply (2): Yes
Please share your knowledge and experience for above questions.

Muhammad Babur Khan
Cell # 00966 582774568
Sent from my iPhone