Skip to main content

RE: [MW:23973] Other Project PQR Can be used New project on Different Clients?

The first question is whether it is in the contract or the project specifications that welding procedures are qualified especially for the project or on the project specific materials. Sometimes that is a requirement and if it is then the previously qualified procedures are not acceptable. If previously qualified procedures are acceptable under the contract then the contractor can submit WPQRs, PQRs or WPARs [depending on whose abbreviation you want to accept for these qualification packages]. They must be submitted complete, with no alterations or omissions and demonstrate compliance with the requirements from the code of practice required for the current project. If they do not meet the current requirements they are invalid and rejected.

 

The next thing is the WPS to be used for production. The WPS is the instruction used on the shop floor for the welding. It should be written to meet the requirements of the specific joint or joints for the current project. It is project specific and hence should be a new document, and it should reference the WPQRs which qualify it. WPSs should be written which cover all the different joint types on the project and all the different welding variants. A matrix should be developed to show all the WPSs and for each one the WPQRs which qualify them. The production of these WPSs and the compilation of the package of WPSs and WPQRs is the job of a qualified welding engineer, who understands all the subtle requirements of the welding code being used.

 

Best wishes

 

Alan Denney

AKD Materials Consulting Ltd

 

From: materials-welding@googlegroups.com [mailto:materials-welding@googlegroups.com] On Behalf Of JIJILAL K M
Sent: 13 December 2015 07:17
To: materials-welding@googlegroups.com
Subject: Re: [MW:23972] Other Project PQR Can be used New project on Different Clients?

 

Dear Mr. Dominic,

 

Your concern is very relevant. It is a common doubt among young professionals.

Since  WPS qualification in an expensive effort by means of time and cost,mostly companies will go for same document qualification by submitting their existing PQR and WPS for review and approval if there is no much deviation in Essential and supplementary essential variables

 .

ASME permits it as the responsibility of manufacturer/contractor.

 

Infact , It is the sole discretion of client engineer  whether approve or go for new PQR.

 

JIJILAL K M

QA/QC Manager,

Jurong Engineering Limited.

TJEL-KCE project,Thailand. 


K.M. JIJILAL

 

 

On 19 November 2015 at 00:43, dominic v.k.dominic <v.k.dominic@gmail.com> wrote:

Dear Expertise,

The contractor submitted other project PQR and approved by some other third party company and client.

My Question: Can used other client approved PQR for this new project and new Client?

In the code (API-1104 and ASME Section -IX) anywhere specified in this matter for Employer can be used other project PQR-If matching According the codes and new client requirements.

If yes, please provide code reference.

 

Thanks in Advance.

Best Regards,

Dominic.

 

 

 

--
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/650131b9-29c8-4683-b02f-cb6265988377%40googlegroups.com.
For more options, visit https://groups.google.com/d/optout.

 

--
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at https://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAHmEnHjWAGXhgQYm7Qxp8yxJDZCpPAgtP2E2R6_Qv6RvXctz8w%40mail.gmail.com.
For more options, visit https://groups.google.com/d/optout.

Comments

Popular posts from this blog

Re: [MW:34105] SA266 GR4N 4 Cycle SPWHT

Hi,  You are correct, Minimum refers to the one cycle for which this part will expose until final work shop PWHT. hence mill test certificate shall include this.  Max. SPWHT, refers to additional cycles of heat treatment that are reserved for future repairs during equipment lifetime.  Again, these simulated no. Of cycles shall be specified in MTC.  The idea is we need to make sure that steel mechanical properties are not compromised upon exposure to multiple repairs (i e 4 cycles in your case).  One could say, if steel is subjected to 4 cycles and is ok, then it should by defacto be good for one cycle, yet, this is wrong assumption cause mechanical problems and microstructure of materials varies accordingly based on no. Of cycles for which material will expose. This is apparent in alloy steel and especially for impact test values as an example.  In your case, this forged CS with properties before PWHT can be understood to be " as forged" condition (i.e. Wit...

Heat tint (temper) colours on stainless steel surfaces heated in air // Heat tint

Introduction The colour formed when stainless steel is heated, either in a furnace application or in the heat affected zone of welds, is dependent on several factors that are related to the oxidation resistance of the steel. The heat tint or temper colour formed is caused by the progressive thickening of the surface oxide layer and so, as temperature is increased, the colours change.   Oxidation resistance of stainless steels However, there are several factors that affect the degree of colour change and so there is no a single table of colour and temperature that represents all cases. The colours formed can only be used as an indication of the temperature to which the steel has been heated. Factors affecting the heat tint colours formed Steel composition The chromium content is the most important single factor affecting oxidation resistance. The higher the chromium, the more heat resistant the steel and so the development of the heat tint colou...

Materails FAQs

Q: What are equivalents for standard Q 235 B (and Q 235 A) for U-channels? (asked by: boris.vielhaber@vait.com) A: DIN Nr. = 2393 T.2, 2394 T.2, EN 10025 W. Nr. DIN 17007 = 1.0038 Design DIN 17006 = RSt 37-2, S235JRG2 (Fe 360 B) Q: What is St DIN 2391 BK material? (asked by: dmcandrews@automaticstamp.com) A: Precision steel tubes, cold-finished/hard. Q: What is C.D.W. Boiler Tube? (asked by: montydude123@yahoo.com) A: Cold Drawn Welded Boiler Tube. Q: WHAT IS W.Nr. 1.4301? PLS TELL US IN EASY LANGUAGUE (asked...