Re: [MW:11110] Hydrotesting of unfired pressure vessel

Dear Venkateswaran,
 
As client (i believe your TPI represent Client) i prefer to do as per operation postion to check the integrity of the skirt and temporary support during HT will harm the vessel during testing.
 
regards
On Thu, May 19, 2011 at 7:33 PM, jayaanil <nethalaanil@gmail.com> wrote:
Dear Venkateswaran,
 
You have to convince your 3rd party for doing Hydro in Horizontal position.
 
See depending upon the access and feasability we can do the test both in Vertical or Horizontal, give some examples to him...in case of Reactors or Columns length will be more than 35mtr, in Such cases we will test them in Horizontal position only at shop floor or manufacturing area.(even though they were designed for Vertical position), Same was accepted by EIL, Lyods,BV ....
 
So be practical ,explain the difficulties and convince them .
On Wed, May 18, 2011 at 2:56 PM, Venkateswaran <k.venkateswaran@ionexchange.co.in> wrote:
 

Hi,all


One of our 3rd party inspector refused to witnessed hydro test of unfired pressure vessel because the actual site erection of vessel is vertical but we offered vessel Hydro at horizontal due to space restriction. vessel diameter 3000mm X 3200 mm longx12 mm thickness.


Construction code ASME section IX.


What is the reason behind the position in doing Hydro test,what will be effect/reason for rejection if the vessel was tested in horizontal position and any standard says regarding this condition.


Pl. suggest.



Regards,


K. Venkateswaran

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

Re: [MW:35289] Welding consumable for S355J2WP material

S355 J2 WP  is a weathering structural steel  It has better atmospheric corrosion resistance. Use E 8018 - W1/W2  Electrodes This is regular...