Thursday, July 22, 2010

[MW:6080] Re: QUALIFICATION OF WELDERS BY PRODUCTION WELDING AS PER AWS D1.1

Acceptable provided the Welding Process should have been qualified
before engaging on Production Welding.

Thanks
Senthil

On Jul 22, 12:30 pm, "Philip, Taiye (Lagos)"
<Taiye.Phi...@deltaafrik.com> wrote:
> As per D1.1 clause 4.19.1.1, welding operator may be qualified by taking
> RT on production welding,
>
> Please clarify if welders also can be qualified in the same way with
> reference to clause?
>
> Regards
>
> Philip Taiye
>
> Principal QA/QC Welding Engineer
>
> (MIPs Quality Control)
>
> DeltaAfrik Engineering Limited
>
> 2nd Floor, City Express Bank Building
>
> Plot 1637 Adetokunbo Ademola Street
>
> Victoria Island, Lagos  Nigeria
>
> Phone: +234-1-461-8508, +2341-461-6137 ext. 1257
> Cell: +234-(0)-803-803-1396
> Fax: +234-1-262-2418
>
> e-mail: taiye.phi...@worleyparsons.com
>
> *** WORLEYPARSONS GROUP NOTICE ***
> "This email is confidential.  If you are not the intended recipient, you must not disclose  or  use the  information contained in it.
> If you have received this email in error,  please notify us immediately by return email and delete the email and any attachments.
> Any personal views or opinions expressed by the writer may not
> necessarily reflect the views or opinions of any company in the WorleyParsons Group of Companies."

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.