Dear All
 
there is no relation between Welder Qualification Code ASME IX and Any Construction code as B31.3 or B31.1 in the Acceptance Criteria of welder qualificatin
 
if ur welder is qualified according to ASME IX he can weld in Power piping projects or Process Piping projects
 
in another case if ur welder is qualified by Production Test he must follow the construction code which he is qualified by .
 
Best Regards ,
ENG. Ahmed Osman
TEL. +213 793092233
        +20 129842855


All new Yahoo! Mail - Get a sneak peak at messages with a handy reading pane
--~--~---------~--~----~------------~-------~--~----~
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
-~----------~----~----~----~------~----~------~--~---

No comments:

Re: [MW:35289] Welding consumable for S355J2WP material

S355 J2 WP  is a weathering structural steel  It has better atmospheric corrosion resistance. Use E 8018 - W1/W2  Electrodes This is regular...