Generally it depends on humidity.

Blasting can be  carried out after 10.00am and generally till 17.00 hrs in the evening when the steel temp. and humidity is conducive.

regards

 

-----Original Message-----
From: materials-welding@googlegroups.com [mailto:materials-welding@googlegroups.com] On Behalf Of Jivan Dhamane
Sent: Tuesday, February 19, 2008 5:58 PM
To: materials-welding@googlegroups.com
Subject: [MW:581] Regarding PWHT and Sand Blasting advice me

 

Dear Friends

 

I have two queries that are as follows please advice me.

 

1.      We are constructing Horton Sphere, at the initial stage our subcontractor had submitted PWHT procedure for whole sphere, but due to some accessories to inserted in the sphere for PWHT purpose they revised PWHT procedure in two parts. That is by Internal Firing Method for whole sphere except (Bottom Centre Crown plate weld) and after welding of Bottom Centre Crown plate weld PWHT is to carry out by Local Electrical Heating Method.

 

By doing so, BVIS Surveyor is asking for 02 Nos. Production Test Coupons (PTC). One for PWHT by Internal Firing Method and another for PWHT by Local Electrical Heating Method. We tried to convince BVIS Surveyor for only one no. PTC as Welding Procedure Specification (WPS), PWHT cycle and other all construction activities are same for both the part but BVIS Surveyor is no satisfied and asking for 02 Nos. PTC.

 

2.      As per painting specifications codes and standard paining shall not carried out when the humidity is above 85%. What time sand/slag blasting shall start in the morning (as water due is present in atmosphere or the surface) and up to what time it shall continue in the evening? As you know India environmental condition and our site is near seashore.

 

Waiting for your reply, till then take care and good bye

 

Regards

 

 

Jivan Dhamane

  


Bollywood, fun, friendship, sports and more. You name it, we have it.</a

P Please don't print this e-mail unless you really need to.

DISCLAIMER:
The information contained in this electronic message and in any attachments to this message is confidential, legally privileged and intended only for the person or entity to which this electronic message is addressed. If you are not the intended recipient, please notify the system manager and you are hereby notified that any distribution, copying, review, retransmission, dissemination or other use of this electronic transmission or the information contained in it is strictly prohibited. Please accordingly also note that any views or opinions presented in this email are solely those of the author and may not represent those of the Company or bind the Company. This message has been scanned for viruses and dangerous content by Mail Scanner, and is believed to be clean. The Company accepts no liability for any damage caused by any virus transmitted by this email. www.essar.com.
--~--~---------~--~----~------------~-------~--~----~
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
-~----------~----~----~----~------~----~------~--~---

No comments:

[MW:35346] Cast-iron welding

Any advice for cast iron welding Sent from Yahoo Mail for iPhone