[MW:34870] FORM QW-483 SUGGESTED FORMAT - Tests Conducted by .........

For the "FORM QW-483 SUGGESTED FORMAT FOR PROCEDURE QUALIFICATION RECORDS PQR", I've had a disagreement with our client / owners during the WPS/PQR review.
Towards the end of the suggested format where it says "Tests Conducted by _____XXXXXXXXXXXX______"; are we supposed to fill in the name of
(1) PIC/QC Engineer/Main Overseer of the PQR from the 'Organization' company (the one who decided on the test coupon size, thickness, electrode, current, amp, WPS, etc. (often our/Organization QC Manager or Senior QC Engineer);
OR
(2) the Person who conducted the Mechanical Testing (Bend, Tensile, macro, hardness, etc.). For (2), the Testing is often done by multiple technicians from 1 testing laboratory, or a different laboratory for NDT (if conducted),or different laboratory for special test (outside the ASME IX testing requirements). So, there often isn't a specific singular person for all the NDT and Destructive testing.

What is supposed to be filled there?

--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/71a333d1-9021-49cd-92de-b8dfd296880dn%40googlegroups.com.

No comments:

[MW:34920] Tubesheet Hole step

Hello Team, I have one question any tolerance given for tubesheet Hole step. Please do needful. Regards, AP  -- https://materials-...