Dear Sirs,
As per ASME B31.3 clause no.341.3.1(a) mentioned P Nos.3,4,5A,5B,5C AND 15 materials examination(RT/UT) shall be performed after completion of heat treatment. But no information for P1 material whether NDT performed before or after PWHT.
Please advise can we perform NDT(RT/UT) before PWHT activity for P1(NACE/H2 service) material or not.
Regards,
Ranajit Chatterjee
9995018265 --
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To view this discussion visit https://groups.google.com/d/msgid/materials-welding/1766993169.S.607.21315.f5mail-224-227.rediffmail.com.1766993764.7778%40webmail.rediffmail.com.
As per ASME B31.3 clause no.341.3.1(a) mentioned P Nos.3,4,5A,5B,5C AND 15 materials examination(RT/UT) shall be performed after completion of heat treatment. But no information for P1 material whether NDT performed before or after PWHT.
Please advise can we perform NDT(RT/UT) before PWHT activity for P1(NACE/H2 service) material or not.
Regards,
Ranajit Chatterjee
9995018265 --
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To view this discussion visit https://groups.google.com/d/msgid/materials-welding/1766993169.S.607.21315.f5mail-224-227.rediffmail.com.1766993764.7778%40webmail.rediffmail.com.
Comments