You need to redo the HT if the welding of temporary support attached to pressure part, refer to your tank construction code. Thanks
Regards
RM
Sent by Maxis from my BlackBerry® smartphone
From: SOHAIB GHNAIMAT <sohaib_cegco@yahoo.com>
Sender: materials-welding@googlegroups.com
Date: Sun, 1 May 2011 10:16:21 -0700 (PDT)
To: <materials-welding@googlegroups.com>
ReplyTo: materials-welding@googlegroups.com
Subject: Re: [MW:10909] Hydrotest-API 650
Re-Hydro test should be done.
Regards,
Sohaib
From: DHANASEKARAN SUBRAMANIAM <subramaniamdhanasekaran7@gmail.com>
To: materials-welding@googlegroups.com
Sent: Sun, May 1, 2011 8:40:39 AM
Subject: [MW:10902] Hydrotest-API 650
Gents,
After the completion of a tank hydro test, some temporary attachment welding has been made on the shell and roof plates.
What action needs to be taken at this stage, kindly provide the action plan with code references.
Your Immediate response is highly appreciated.
--
WITH REGARDS,
DHANASEKARAN .S ,
DHANASEKARAN .S ,
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
No comments:
Post a Comment